One, check before driving:

1, check whether the oil in the tank is sufficient, whether there is water or impurities in the oil

2, start the pump, check whether the oil pump, oil pipe meets the requirements, whether there is oil leakage and tubing blockage

3, check whether the dust protection facilities are complete, whether the water pipe is unobstructed, and whether the dustproof effect is good or not

4, check the broken chamber for minerals and other debris, such as found in a timely manner excluded

5, check whether the discharge hopper conforms to the requirement of use and whether the screw is loose or not

6 check whether the electrical accessories are complete and whether the switches are in the parking position

7, check whether there is any obstacle to the operation of the equipment around the equipment

Two, driving notes:

1, received the next process permits to drive the signal, you can operate in accordance with the order in order to drive the car, first open the pump, to be installed after the pump is normal, and then open the main equipment

2, before the equipment starts, check whether there are any work or obstacles around it

3, after starting the equipment, you should check the circulation of lubricating oil and the operation of other parts in detail

4, after checking to confirm that the machine can operate normally, you can notify the previous process to drive to the mine

5, check the size of ore discharge and dust prevention facilities meet the requirements, if there is discomfort, should be adjusted immediately

Three, running inspection:

1, check whether the normal hydraulic oil temperature, oil pressure should be maintained at C /Mpa square meters, the oil return temperature does not exceed 55 degrees, the inlet temperature does not exceed 45 degrees.

2, check whether the equipment is normal, pay attention to the motor temperature rise and current fluctuations, no overload operation

3, check the Department screw in the operation of the equipment is loose and fall phenomenon, whether the fixed lining plate signs of loosening, the sound of the Department is normal

4, check whether the equipment belongs to the oil leakage

5, often check whether the ore size meets the requirements, to discharge ore funnel is smooth, found problems solved in a timely manner

6, it is strictly prohibited to pull the brakes with the load. The major accidents are not covered by this restriction, but the site must be protected.

click to see the cone crusher parts introduction

Hunan Fengwei Wear Parts Foundry covers an area of more than 20 thousand square meters, and has a plurality of sand mold and EPC process production line, equipped with advanced laboratory and quality inspection equipment, with an annual output of more than 1 tons of wear-resistant parts enterprises always adhere to the wear-resistant casting production and research direction, according to the characteristics of various working conditions of crushing and grinding equipment and materials of its own, with high-quality raw materials, make the product toughness and wear degree reached 1.2 to 1.5 times that of similar products. Welcome new and old customers call to map custom.